1. 系统概述
1 General Description Of The System
汽轮机安全监测仪表系统(Turbine Supervisory Instrument,简称TSI)是一种可靠的连续检测汽轮发电机转子和汽缸的机械工作参数的多路监控系统,可以显示机组状态,为记录仪和计算机系统提供输出信号,并在超出预置的运行极限时发出报警,此外,还能使汽轮机自动停机和提供用于诊断性估算的各种测量数据。
Turbine Supervisory Instrumentation ( Turbine Supervisory Instrumentation , referred to as the TSI ) system is a reliable continuous detection of mechanical operating parameters of the turbine generator rotor and cylinder multi-channel monitoring system that can display unit provides analog output signals for the recorder and computer systems. TSI also output digital signals for alarm and trip when the input signals exceed the limit.
本机组TSI采用的是BENTLEY3500系列模件。 This site use the 3500 series modules form BENTLEY.
该保护系统设计有冗余的电源模件,由双路电源供电,任一路电源丧失可发出报警,保证系统安全可靠。
The protection system is provided with a redundant power supply module and is powered by double passage power supply. Alarm can be issued when any one power supply is lost to ensure safety and reliability of the system.
TSI的测量回路是由探头、前置放大器、插件式组装仪表等组成。探头和前置器在出厂前已成套进行了线性校准,安装时要成套安装。
Measurement loop of TSI consists of probe, front-mounted amplifier and socket type assembly instruments. Linear calibration is carried out on probe and front-mounted amplifier before leaving the factory and they should be installed in set.
2. 编制目的
2 Preparation of purpose
编写本措施的目的是规范TSI系统的调试行为,确保设备、人身不受伤害。保证系统调试保质、保量、有序进行。
The purpose of this procedure is to write a specification TSI system commissioning behavior, ensure that the equipment and person safe. Ensure that the system commissioning quality and orderly manner.
Page 1 of 10
3.调试前的应具备的条件
3 Necessary Conditions and Preparation before Commissioning
3.1 TSI控制设备安装完毕,电源具备条件,就地与TSI机柜的接线正确,线间绝缘符合要求,抗干扰措施符合要求。
3.1 Installation of TSI control equipments is finished. The power for TSI is OK. Wiring between field and the TSI cabinet is correct, insulation between lines meet requirements, and anti interference measures comply with requirements.
3.2 汽机本体具备试验条件:各轴承盖开启,探头固定支架安装完毕,汽机处于冷态。 3.2 Main body of the turbine possesses test conditions: all bearing covers are opened, installation of fixing supports of probes is finished and turbine is in cold state. 3.3 汽轮机推力盘紧靠工作推力瓦或非工作推力瓦。
3.3 Thrust disc of the turbine is very close to working thrust block or non-working thrust block.
3.4 保护、报警定值齐备。
3.4 Set points of protections and alarms are perfect.
4.调试工作内容及分工
4 Commissioning Items and Procedures
4.1 调试项目
4.1 Commissioning Items 4.1.1 TSI系统安装检查
4.1.1 Check installation of the TSI system 4.1.2 TSI系统送电及恢复
4.1.2 Power initialized and recovery of the TSI system 4.1.3 TSI系统测量装置的试验
4.1.3 Test of measurement devices in the TSI system 4.1.4 报警、跳闸定值校核
4.1.4 Check set points of alarm and trip 4.1.5 TSI系统保护系统试验
Page 2 of 10
4.1.5 Test of protection systems in the TSI system 4.2 调试程序
4.2 Commissioning Procedures 4.2.1 TSI系统送电及程序恢复
4.2.1 Power initialized and program recovery of the TSI system 4.2.2 电源冗余试验
4.2.2 Power supply redundancy test
本系统设计为双路电源冗余供电,当失去一路电源时仪表工作状态不应改变。且发出报警信号到相应的报警系统。
The system is designed into double passage power redundant power supply. When one power supply is lost, working state of instruments will not be changed and an alarm signal will be sent to corresponding alarm system. 4.2.3 检查测量信号的校验记录
4.2.3 Check calibration records of measurement signals 4.2.4 现场安装和调试
4.2.4 Field installation and commissioning test
1) 轴向位移和胀差传感器的安装整定
1) Installation and commissioning record of rotor position and differential expansion sensor
轴向位移传感器的安装整定记录表
Installation and commissioning record of rotor position sensor: 指示值 [mm] 项目 传感器类型 间隙电压[Vdc] Indicated value Items Sensor type Gap voltage TSI DCS 1号轴位移 NO.1 RP 2号轴位移 NO.2 RP 3号轴位移 NO.3 RP 4号轴位移 NO.4 RP 高压胀差传感器的安装整定记录表
Installation and commissioning record of differential expansion sensor of HP
Page 3 of 10
330703 330703 330703 330703