目 录
1. 概述 ............................................................................................................................................ 1
1.1 工程概况 ........................................................................................................................... 2 1.2 编制依据 ........................................................................................................................... 2 2. 施工布置 .................................................................................................................................... 2
2.1 施工通道布置 ................................................................................................................... 2 2.2 垂直人行通道布置 ........................................................................................................... 2 2.4 供水、供电系统布置 ....................................................................................................... 4 2.5 施工排水 ........................................................................................................................... 4 2.6 混凝土生产 ....................................................................................................................... 4 3. 施工程序及工艺流程 ................................................................................................................ 4
3.1 施工程序 ........................................................................................................................... 4 3.2 施工工艺流程 ................................................................................................................... 5 4. 混凝土分层分块和模板配置 .................................................................................................... 5
4.1 混凝土分层分块(见图2) ............................................................................................ 5 4.2 混凝土分层 ....................................................................................................................... 5 4.3 模板选型 ........................................................................................................................... 7 5. 混凝土施工方法 ........................................................................................................................ 7
5.1 钢筋施工 ........................................................................................................................... 7 5.2 模板施工 ........................................................................................................................... 8 5.3 预埋件施工 ....................................................................................................................... 9 5.4 混凝土拌制及运输 ........................................................................................................... 9 5.5 混凝土入仓方式 ............................................................................................................... 9 5.6 混凝土浇筑方法 ............................................................................................................. 10 5.7 混凝土平仓和振捣 ......................................................................................................... 10 5.8 模板变形观测 ................................................................................................................. 10 5.9 拆模 ................................................................................................................................. 11 5.10 施工缝处理 ................................................................................................................... 11 5.11 混凝土养护 ................................................................................................................... 12 5.12 过流面保护 ................................................................................................................... 12 5.13 混凝土雨季施工 ........................................................................................................... 12 5.14混凝土温控措施 ............................................................................................................ 13 6. 施工资源配置 .......................................................................................................................... 13
6.1 施工人员配置计划 ......................................................................................................... 13 6.2 施工设备和模板配置计划 ............................................................................................. 13 7. 质量保证措施 .......................................................................................................................... 14 8. 安全保证措施 .......................................................................................................................... 15
8.1 施工危险源和安全管理难点分析 ................................................................................. 15 8.2 安全技术措施 ................................................................................................................. 15 8.3 安全管理措施 ................................................................................................................. 17 9. 文明施工 .................................................................................................................................. 19
1. 概述
1.1 工程概况
响水水库取水兼放空隧洞布置于坝区左岸,分为取水口和引水隧洞,大坝施工期间兼做导流洞。取水口采用岸塔式布置型式,总长13.6,净空尺寸宽×高=2.2×1.9m。塔体建基面高程为▽1529.0m,进水口底板高程为▽1530.0m,顶板高程为▽1533.0m,塔体顶部高程为▽1566.2m,塔体顶部与左岸▽1566.2m平台间采用交通桥连接成一体。进水口结构主要由底板、胸墙、塔体和封堵闸门组成,其中塔体内布置有工作闸门井、拦污栅闸门井和通气孔组成,塔体顶部设有闸门启闭机室。具有结构复杂、塔体高、孔洞多、施工难度大等特点。其结构混凝土强度等级为C20,门槽二期混凝土强度等级为C25。进水口塔体混凝土主要工程量详见下表1。
表1 进水口塔体和拦污栅混凝土浇筑工程量表 工程项目 C20混凝土 钢筋制安 C25混凝土 金属结构及设备 1.2 编制依据
1)现行国家和行业相关施工技术规范、标准;
2)项目部 [2016] 技008号《导流兼取水放空隧洞施工组织设计》及其监理工程师批复意见;
5)进水口结构布置图《兴仁-响水-施工-水工-取水管-(01~05)》;
2. 施工布置 2.1 施工通道布置
按照坝区施工平面布置,结合右岸电站进水口的结构型式和现场实际情况,进水口混凝土施工道路布置如下:
混凝土拌合站→新建上坝公路 → 左岸坝肩平台 →3#临时施工道路 →进水口 → 工作面。 2.2 垂直人行通道布置
单位 m3 t m3 工程量 960 57.98 150 备 注 边坡回填砼以实际发生量计 另见详图