目 录
一、编制依据 ................................................................................................................ 0 二、工程概况 ................................................................................................................ 0 三、施工准备 ................................................................................................................ 1
3.1施工复测 ........................................................................................................................................ 1 3.2核对设计文件 ............................................................................................................................... 1 3.3岗前培训 ....................................................................................................................................... 1 3.4征地拆迁 ....................................................................................................................................... 1 3.5物资准备 ....................................................................................................................................... 1
四、机械设备及人员配置 ............................................................................................ 2
4.1机械配置表 ................................................................................................................................... 2 4.2人员配置表 ................................................................................................................................... 2
五、施工方案及方法 .................................................................................................... 3
5.1施工方案 ....................................................................................................................................... 3 5.2施工方法 ....................................................................................................................................... 4
六、质量保证措施 ...................................................................................................... 15
6.1配备强有力的项目班子 ............................................................................................................. 15 6.2强化项目的技术、质量、检测力量 ......................................................................................... 15 6.3质量管理制度 ............................................................................................................................. 16 6.4分项工程施工质量保证措施 ..................................................................................................... 21 6.5保证施工工艺的质量措施 ......................................................................................................... 23 6.6保证工程材料质量的措施 ......................................................................................................... 23 6.7确保施工检测数据准确性 ......................................................................................................... 24 6.8加强施工的沉降观测与评估 ..................................................................................................... 24 6.9控制和防止质量通病的措施 ..................................................................................................... 24 6.10已完工程和设备的保护措施 ................................................................................................... 25
七、施工排水和雨季施工措施 .................................................................................. 26 八、施工安全保证措施 .............................................................................................. 26
8.1安全保障管理措施 ..................................................................................................................... 26
九、文明施工措施 ...................................................................................................... 28
9.1健全体系 ..................................................................................................................................... 28 9.2完善制度 ..................................................................................................................................... 28 9.3落实措施 ..................................................................................................................................... 29
十、环境保护措施 ...................................................................................................... 32
云桂线(云南段)站前工程YGZQ-2标段 **隧道出口D2K370+620~DK373+809.85区间路基施工方案
一、编制依据
1.1新建铁路云桂线(云南段)指导性施工组织设计。
1.2新建铁路云桂线(云南段)站前工程YGZQ-2标段图纸。 1.3新建铁路云桂线(云南段)站前工程YGZQ-2标段工程量清单。 1.4铁路工程施工组织设计指南(铁建设[2009]226号)。
1.5现场施工组织调查及当前铁路建设的技术水平、管理水平和施工装备水平。
1.6国家及铁道部现行施工规范、工程质量检验评定标准、试验规程、安全规程。
1.7中铁二十五局集团有限公司通过质量体系认证中心认定的《质量手册》和《程序文件》。
1.8路堤填筑试验段成果报告。
1.9《客运专线铁路路基工程施工质量验收暂行标准》(铁建设[2005]160号)
1.10国家及地方关于安全生产和环境保护等方面的法律法规。 二、工程概况
D2K370+620~DK373+809.85区间路基位于云南省文山州广南县境内,起始里程D2K370+664.074(短链前)~D2K370+800(短链后),全长3.18公里(含**隧道2703m,DK370+847~DK373+550)。工程类型主要有:路基土石方开挖与填筑、松软土地基处理工程、路堑坡面防护等。地基加固处理主要有旋喷桩、重锤夯实等。边坡防护主要采用片石混凝土挡墙、桩板挡土墙、框架锚索梁、种植物防护等形式。
路基工程主要工程数量见下表:
路基工程主要工程数量 工程名称 挖土方 区间路基 挖石方 级配碎石 混凝土及砌体 绿色防护 土工合成材料 路基附属旋喷桩 工程 线路防护栅栏 路基地段电缆槽 挡土墙片石混凝土 单位 立方米 立方米 立方米 立方米 平方米 平方米 米 公里 米 圬工方 工程数量 50434 17633 8592.6 2509 4490 4760 1478.71 0.6 340 3025 路基 三、施工准备
3.1施工复测
建设单位组织设计院进行交桩后项目经理部立即组织精测队与工程师按设计提供的施工设计资料,对线路中线GPS控制桩、水准点高程进行复测,根据复测成果形成复测报告。复测结果报经监理和建设单位批复后,组织定位放线,对路基工程布设精密导线网、水准网,埋设永久桩和护桩。
3.2核对设计文件
接到设计文件后,结合设计技术交底,分部总工程师组织有关技术人员全面熟悉设计标准、技术条件及要求,核对设计文件,充分了解设计意图,核对地形地貌、工程地质和水文地质,编写会审记录。如现场与设计不符,及时与设计单位联系,同时抄报监理与建设单位。
3.3岗前培训
针对本工程标准高、规模大的特点,组织技术人员和相关专家对管理人员、技术工人、安全员等进行全员培训及技术交底。项目分部、架子队实施层层交底并做好记录。特殊工种必须持证上岗。
3.4征地拆迁
路基红线内全部拆迁工作都已完成。 3.5物资准备