AP1000 design specification AP1000 设计规范 Stone & Webster, INC 100
technology center drive Stoughton, MA 02072 AP1000 design specification Revision 1 Page 1 of 49 Assigned to Open items no. SWI, inc 开口项 AP1000技术规格书编号版次 1 页数 43 委托 APP-SS01-Z0-002 Alternate number 备份文件编码: REV. 修订版 Equipment: 设备 Erection of Structural Steel 钢结构安装 Shop order/ wbs: 工作分类细目: System: 系统 P.E. certification 专业工程师鉴定 P.E./date 日期 Electronic filename Electronic file format 电子文件名 电子文件格式 APP-SS01-Z0-002 Rev1.doc Microsoft word 2003,SP2 DCP#REV. incorporated 对该文件的变更建议: Electronic file description 电子文件描述 Design specification for erection of structural steel 钢结构安装设计规范 2009 Westinghouse electric company LLC and/or stone& Webster, INC. 2009 西屋电气公司 LLC和/或石伟,INC Westinghouse proprietary class 2 and/or stone &Webster confidential and proprietary 西屋专利2级和/或石伟机密文件和专利 This document is the property of and contains proprietary information owned by Westinghouse electric company LLC and/or is the property of and contains confidential and proprietary information owned by stone &Webster inc. and/or their affiliates, subcontractors and suppliers. It is tran smitted to you in confidence and trust, and you agree to treat this document in strict accordance with the terms and conditions of the agreement under which it was provided to you. 本文件版权归西屋电气公司和/或其分包商和供应商所有,文件包含该公司专利信息。基于对贵方的信任,将文件转发贵处,贵方应严格按照协议上的条款和规定使用该文件。 QA category I, class NSR(nuclear safety related) 质保等级I,NSR分类(与核安全相关) Originator(s) 起草人 Signature/date M.Seniwongse 签字/日期 reviewer(s)评审人 Signature/date P.Smith 签名/日期 Responsible Functional Manager Signature/date 责任职能经理 签名/日期 W.J.Pananos Verifier(S) 校对员 R.Widen Signature/date 签名/日期 Verification method independent review 验证方法:独立评审 Quality assurance Signature/date 质保部 签名/日期 K.Fahey **plant applicability 适用电站 all AP1000 plants except: none 所有AP1000电站 □Only the following plants 仅下列核电站: Applicability review** Signature/date 适用性评审: 签名/日期 C.Metcalfe Responsible manager Signature/date 责任经理: 签名/日期 M.Scanlon * Approval of the AP1000 responsible manager signifies that the document is complete, all required reviews are complete, electronic file is attached, and the document is released for use.
AP1000责任经理的批准意味着该文件及所有要求的审核都是完整的,并附有电子版文件,且文件已发布使用。
Number: 编码 APP-SS01-Z0-002 ISSUE DATE: 发布日期 Revision 1版
Design specification
For
Erection of Structural Steel 钢结构安装技术规范 中国AP1000项目
Approval 批准 date 日期
Prepared by编制: M.Seniwongse Lead discipline engineer
主导科目工程师: W. Pananos Design verifier (safety related)
设计审核(与核安全相关) P.Widen Discipline chief engineer/specialist
科目总工程师/专家: P.Smith Construction工程部: R.Macleod Quality assurance质保部: K.Fahey Procurement采购部: N/A Project engineer项目经理: M.Scanlon
QA Category I, II,III(NSR, RTNSS, NNS) 质保等级I,II,III(NSR, RTNSS, NNS)
This document, including certain of its background information contains the proprietary and confidential information of stone& Webster international, inc. and is to be returned upon request. Its contents may not be copied. Disclosed to third parties, or used for other than the express purpose for which it has been provided without the prior written consent of stone &Webster international, inc. this document does not constitute a ―work for hire‖.
该文件,包括其包含石伟公司专利和机密信息的相关背景信息,在石伟的要求下需要返还。未经石伟公司事先书面同意,不得复制文件内容,也不能泄漏给第三方或用于其它目的。该文件属技术文件,不属商业文件。
变更记录 Date Rev Change Pages affected 日期 版次 变更 受影响的页码 9/4/08 0 Contract deliverable: CFC issues None 合同交付项:CFC版 无 8/20/2009 1 Contract deliverable: CFC issues 6,10-14,17,34,40合同交付项:CFC版 ,41-43 Revised definition Section 1.0, revised Section 2.0 to clarify work not included, added references Section 3.0, revised technical requirements Section 4.0, revised QA Section 5.0, Incorporated E&DCR-SWI-C-045 in Section 3.0, Incorporated E&DCR-SWI-C-033 in Section 4.5.9, Added Appendix A and B forms 修订了1.0节的定义,修订了2.0以澄清未包括的工作,增添了3.0的参考资料,修订了4.0中的技术要求,修订了5.0 QA部分。合并了3.0中E&DCR-SWI-C-045;合并了4.5.9中E&DCR-SWI-C-045。增添了附录A和B表格。 See cover page Incorporated EDCR APP-SS01-GEF-002. Incorporated by reference EDCR CPP-4000-GEF-022,CPP-4000-GEF-023, CPP-4000-GEF-024, CPP-SP02GEF-005, CPP-SS01-GEF-004. Added Field Coating Specification. Updated Applicable Documents. Added clarification for SMAW weld filler metal. Revision 1 incorporated EDCR-SWI-C-045, which was never issued and changed AWS D1.1 code year from2006 to 2000 8.12 8.13
TABLE OF CONTENTS
目录
ERECTION OF STRUCTURAL STEEL 钢结构安装技术规格书 1.0 DEFINITIONS 定义 2.0 SCOPE 范围
3.0 APPLICABLE DOCUMENTS 适用文件 4.0 REQUIREMENTS 要求 4.1 Project Type 项目类型 4.2 Extent of the Work 工作范围 4.3 Technical Requirements 技术要求
4.3.1 Qualifications of Erector 安装方资格认证 4.3.2 Prequalification of Erectors 安装方资格预审 4.3.3 Materials 材料
4.3.4 Shop and Erection Drawings by Purchaser or Fabricator
购买方或制造方提供的加工图及安装图 4.4 CONSTRUCTION MANAGEMENT 施工管理 4.4.1 Coordination Meetings 协调会议
4.4.2 Critical Path Method and Progress Report 关键路径方法和进度报告 4.4.3 Safety Requirements 安全要求
4.4.4 Assembly Lift Plan by Erector 安装方制定的组件吊装方案 4.4.5 Site Condition Coordination with Fabricator 与制造者协调现场条件 4.4.6 Receiving, Inspection and Storage 接收,检查和存储 4.4.7 Pre-Erection Activities 预安装处理 4.5 ERECTION 安装 4.5.1 General 概述
4.5.2 Structural Stability During Erection 安装过程中的结构稳定性 4.5.3 Base Plates 底板
4.5.4 Grouting of Base Plates 底板灌浆 4.5.5 Field Connections 现场连接
4.5.6 High Strength Bolts 高强度螺栓 4.5.6.1 General 概述
4.5.6.2 Tension Measuring Device 张力测定仪 4.5.6.3 Use of Washers 垫圈的使用
4.5.6.4 Tightening of High Strength Bolts 高强度螺栓的固定 4.5.6.5 Inspection of Bolt and Bolt Installation 螺栓检查及安装 4.5.7 Structural Bolts 结构螺栓 4.5.8 Welded Connections 焊接连接 4.5.9 Inspection of Welds 焊缝检查 4.5.10 Correction of Errors 校正误差
4.5.11 Erection Alignment of Structures 结构安装定位
4.5.12 Deferred Erection Due to Other Trades 其他原因导致的安装延期 4.6 ERECTION OF STEEL JOISTS 钢托梁安装 4.7 ERECTION OF FLOOR PLATE 楼板安装
4.8 ERECTION OF METAL FLOOR GRATING 金属楼板栅栏的安装 4.9 BANDING 捆绑
4.10 STEEL DECKING FOR FLOORS AND ROOFS
用于楼层及屋顶的钢盖板 4.11 SHEAR CONNECTORS 抗剪连接
4.12 ERECTION OF STEEL STAIRS 钢楼梯的安装
4.13 ERECTION OF STEEL HANDRAILS AND POSTS 钢栏杆和柱子的安装 4.14 ERECTION OF MISCELLANEOUS STRUCTURAL STEEL
零星钢结构的安装
4.15 PROTECTIVE COATINGS 保护层
4.16 AS-BUILT DRAWINGS, FINAL INSPECTION AND CERTIFICATE 竣工图纸,终检和竣工证明
4.17 Bridge Crane Runway Rain Erection Requirement 5.0 QUALITY ASSURANCE 质量保证
APPENDIX A SAMPLE TEST, INSPECTION, AND DOCUMENTATION FORM 附录A 样品试验、检查和文件表