330KV架线施工作业指导书.

目 录

1 2 3 4 5 6

适用范围 .................................................................................................................................. 1 编制依据 .................................................................................................................................. 1 作业内容 .................................................................................................................................. 1 工程概况 .................................................................................................................................. 1 工艺流程 .................................................................................................................................. 1 准备工作 .................................................................................................................................. 2 6.1 6.2 6.3 6.4 7

技术交底 ...................................................................................................................... 2 工具准备 ...................................................................................................................... 2 跨越架搭设 .................................................................................................................. 4 放线滑车安装 .............................................................................................................. 5

张力放线工艺过程 .................................................................................................................. 6 7.1 7.2 7.3 7.4

牵引场及张力场布置 .................................................................................................. 6 展放牵引绳 .................................................................................................................. 9 张力展放导线绳及地线 .............................................................................................. 9 张力展放导线 ............................................................................................................ 10

张力放线的机具配置 ............................................................................................................ 13 8

紧线及附件安装 .................................................................................................................... 17 8.1 8.2 8.3 8.4 8.5

工艺流程 .................................................................................................................... 17 紧线前的准备工作 .................................................................................................... 18 过轮临锚 .................................................................................................................... 19 松锚升空 .................................................................................................................... 20 弧垂观测及弛度调整 ................................................................................................ 21

8.6 8.7 8.8 8.9 8.10 9

划印 ............................................................................................................................ 22 耐张塔平衡挂线 ........................................................................................................ 23 导地线接续 ................................................................................................................ 25 附件安装 .................................................................................................................... 25 工器具配置 ............................................................................................................ 28

保证质量措施、质量标准及检验要求 ................................................................................ 31 9.1 9.2 9.3 9.4 9.5 9.6 9.7

导线的保护 ................................................................................................................ 31 导线损伤处理 ............................................................................................................ 33 交叉跨越要求 ............................................................................................................ 34 绝缘子的检验 ............................................................................................................ 34 螺栓穿向 .................................................................................................................... 35 铝包带的使用 ............................................................................................................ 36 其它附件要求 ............................................................................................................ 36

10 安全措施、环境保护和文明施工 .................................................................................... 36 10.1 10.2 10.3

重大危险源识别 .................................................................................................... 36 安全措施 ................................................................................................................ 37 文明施工要求 ........................................................................................................ 41

1 适用范围

本方案适用于赞比亚330kV线路放紧线施工。

2 编制依据

合同文件

我公司制定的符合GB/T24001-2004标准的质量、安全、环境体系程序文件。 我公司现有的施工资源、技术水平和管理模式及施工效率。

我公司质量、职业健康安全和环境管理体系《管理手册》和《程序文件》(2010版)及其它现有项目管理制度。

Overhead line 2010-架空线路

3 作业内容

放线施工准备、张力放线、紧线及附件安装的全过程。

4 工程概况

该项目为卡里巴北至凯富峡西输电线路项目 KK330KV 输电线路第一标段工程。电压等级:330kV;线路长度:64.5公里。线路沿线地区地形较为复杂,有丘陵、山地。

5 工艺流程 转场

平衡挂线 设备进场 展放牵引绳 展放导地线 1 搭设跨越架 放紧地线 间隔棒安装 紧线 附件安装 引流安装