一、工程概况 ...................................................................................................... 2 二、编制依据 ...................................................................................................... 3 三、地质情况 ...................................................................................................... 3 四、施工方案及计算书 ...................................................................................... 8 五、施工方法 .................................................................................................... 12 1、灌注桩施工 ............................................................................................ 12 2、搅拌桩施工 ............................................................................................ 15 3、拉森钢板桩施工 .................................................................................... 18 4、基坑降水及开挖 .................................................................................... 19 5、基坑回填 ................................................................................................ 23 6、雨季施工措施 ........................................................................................ 24 六、管理体系安排 ............................................................................................ 25 七、安全文明措施 ............................................................................................ 25 八、应急预案 .................................................................................................... 26
1-
作者:蒋铖
一、工程概况
城区防洪排涝改造工程(2016年度)一标段为新建东长春河闸站 东长春河闸站,闸孔净宽为8m,采用钢筋砼坞式结构,配弧形下卧式钢闸门。两泵站在闸首北侧单侧布置,水泵型号800QGL-160双向潜水贯流泵,单泵流量2.0m3/s,扬程2.43m,叶片安放角+2°,电动机功率为75KW。
闸站东侧是体育场游泳池。 闸站西侧是体育弄桥。
闸站南侧是太仓市经贸小学,已与学校协商进行围挡搭设。 闸站北侧有两栋商品房,东侧商品房已协商进行拆迁,西侧商品房距本工程闸站基坑开挖线仅4.5米左右。目前,商品房内仅剩余一户居民还未签拆迁协议。我单位拟定方案为在东侧进水池位置打设拉森桩,先进行闸室施工,待东侧房屋拆迁后移至砼结构边线外侧。
2-
作者:蒋铖
二、编制依据
1、 城区防洪排涝改造工程(2016年度)一标段设计图纸; 2、 城区防洪排涝改造工程(2016年度)一标段地质报告; 3、《建筑基坑支护技术规程》JGJ120-2012; 4、《地基与基础工程施工及验收规范》GBJ20283;
三、地质情况