A new project manager is planning a complex hardware installation project.
The
team
consists
of
13
people
who
are
experts
in
their
fields.
The
project
manager
does
not
want
to
micromanage
the
project.
How
far
should
he
decompose the work?
A. As small as possible because the work is complex
B. As large as possible because he is dealing with experts
C. To 1000-hour tasks because he is dealing with experts
D. To about 80-hour tasks because it will make the work less complex
1.
一个新项目经理正在规划一个复杂的硬件安装项目。这个团队由
13
名成员组成,他们
都是各自领域的专家?/p>
这个项目经理不想管理此项目所有细节?/p>
他需要将工作分解到何种程
度?
A
?/p>
因为项目很复杂所以要尽可能细
B
?/p>
尽可能分解的要大,因为他在与专家们合?/p>
C
?/p>
分解?/p>
1000
小时的任务,因为他在与专家们合作
D
?/p>
分解?/p>
80
小时左右,因为这样可以减少工作复杂程?/p>
2
?/p>
The customer wants to make a major change to the scope of work when the
project is mostly complete. The project manager should?
A. Make the change
B. Inform the customer of the impact of the change
C. Refuse the change
D. Complain to management
2.
项目快要完成时客户想对工作范围作一大的变更。项目经理应该:
A
.进行变?/p>
B
.将变更造成的影响通知客户
C
.拒绝变?/p>
D
.向管理当局抱?/p>
3. A client has asked you to add scope of work to the project. The project is
under budget and a little ahead of schedule. What should you do?
A. Approve the change
B. Let the client know the effects of the change on the project
C. Ask approval from the sponsor for making the change
D. Get approval from the configuration change board
3.
客户要求
你增加项目的工作范围,此项目在预算之内进度稍微提前。你应该做什么?
A
.批准这个变?/p>